Wednesday, February 8, 2017

Week 23: Spring Semester Begins

This is the first week of the semester of Spring 2017, and we were reminded about the dates of the Paseo Public Prototyping Challenge and acknowledge that we have around two months to work with the rest of the sub-teams to finish the project. The aim is to finish the track sections early in order to allow for other teams to test and make changes, but more specifically the short term goal is to finish a die allowing for 0.25" aluminum stock to be bent and a measuring block to quantify output.

We are also going to help the solar team to build their ribs which requires their dimensions including arc length and bend radius.

Kevin has more specific information in this week's blog post about the state of other teams and where we stand. (Click Here.)